
May 19, 2008 – Orange Road Bridge Project Update
The County Engineer is nearing completion on final engineering
plans for the new Orange Road bridge. The project team is currently
negotiating with affected property owners for the necessary right
of way to build the new bridge. Construction on the new bridge
is scheduled to begin this fall, with completion of the new bridge
scheduled for summer 2009.
The first phase of the project will include construction of
a new bridge located about 200 feet north of the existing bridge,
connecting a realigned Orange Road to State Route 315. A temporary
stop-controlled intersection will be built while plans for the
proposed roundabout are finalized. The second phase of the project
will include construction of a single lane roundabout at the
intersection of Orange, Carriage and State Route 315. The new
bridge will be built to accommodate the roundabout and no bridge
modifications will be necessary for the second phase of the project.
A construction schedule for the roundabout will be announced
when it becomes available.
September 14, 2007: Orange Road Bridge Closed Until
Further Notice
The County Engineer’s Office is currently evaluating the
feasibility of repairs to the West Orange Road bridge over the
Olentangy River. The current estimate of repairs that would be
necessary to reopen the bridge at the current 3-ton load limit
is about $300,000, which includes replacement of the existing
steel beams that support the wood decking as well as repairs
to the west abutment. Construction would take about 3 months.
Delaware County is committed to the prudent use of taxpayer
dollars and wants to make the most reasonable decision regarding
such a large expenditure of road and bridge funds on a one-lane
bridge with limited service life remaining and reduced load capacity.
Plans for future reuse of the 109 year old bridge have been under
discussion for some time and include ideas such as a dedicated
pedestrian crossing at the current site or moving the bridge
to a planned pedestrian facility at another location.
Right of way and construction plans for the new bridge to be
built about 200 feet north of the existing bridge are currently
under design. The Engineer’s Office expects to start purchasing
necessary right of way for the new bridge this fall. Construction
is planned to start later in 2008.
The Engineer’s Office
appreciates the patience of all area residents inconvenienced
by this closure. Additional information
will be released when it is available.
August 29, 2007: Orange Road Bridge Closed Until Further
Notice
Due to the discovery of recent deterioration in the bridge deck
system during a regularly scheduled structural inspection, the
West Orange Road bridge will be closed while the County Engineer
evaluates the repair options.
The deterioration that was discovered during the inspection
is related to the wood decking and the steel beams that support
the deck timbers. The Engineer is concerned about localized deck
system failures and/or holes in the deck that could potentially
damage vehicles crossing the bridge. While the steel stringers
that support the timber deck are not a main structural part of
the bridge that could cause catastrophic failure of the bridge,
any failure in a bridge member can potentially cause property
damage and/or injury.
The safety of the motorists using the bridge is of paramount
importance to the County Engineer's Office, and for this reason
the bridge will remain closed until the Engineer determines what
repairs can be made. Traffic will be detoured to Home Road.
Please
monitor the Web site for additional details as they become available.
You may also visit the Delaware County Engineer's Office Web
site at www.delawarecountyengineer.org.
About the Project Delaware County is nearing completion of the preliminary
engineering studies on the Orange Road bridge
project located just north of Powell, Ohio.
As we have said from the beginning of the project,
public comments and suggestions are very important as a guide
for the
engineer's
office. Many residents have responded and we thank them.
Why the project is necessary
The existing bridge is structurally deficient and functionally
obsolete based on its reduced structural capacity, width and
sight distance. The project team is committed to providing
a safe and efficient river crossing to the traveling public.
What’s been done so far?
Project engineers have analyzed existing capacity and safety
conditions. There has also been active seeking of public
input through this Web site and meetings with various stakeholders.
This research has allowed us to develop a purpose
and need for the project and feasible
roadway alternatives. The first open house was held on April
26 to present these findings. A subsequent open house was
held on December 13 to present the preferred alternative. Go
here for exhibits and handouts displayed at these
events, and to give us your input on these findings.
So what’s next?
Project engineers will perform detailed engineering and prepare
final mitigation plans. It is estimated that the engineering
and public involvement will be underway through most of 2007.
Although much depends on coordination with other public agencies,
it is anticipated that any construction will not occur until
2008, and would likely take about 12 months to complete. There
are still several key elements to which Delaware County needs
your input, including what should be done with the existing bridge
and what types of aesthetic design elements should be incorporated
into the project? There will be a third open house in 2007, stay
informed by signing
up for email bulletins.
Questions?
If you can’t find what you’re looking for in our
frequently asked questions, please contact Robert Riley, Delaware
County Project Manager, by calling 740-833-2400 or by e-mailing
info@orangeroadbridge.org.
|